Houzz Logo Print
apreston0

New tile floor and bathroom fixtures, what to do you start with first?

apreston0
Год(а)/Лет назад: 7

Hi,

I would like to replace the old tile floor, old sink, old light fixture and old tub and shower unit with new items. My question is, do you replace the tile floor last?

Комментарии: 3

  • acm
    Год(а)/Лет назад: 7

    In terms of actual laying it, you usually do the tub and then the tile and then the vanity, etc., on the finished floor.

    In terms of picking, start with the vanity, then tile, or maybe the two in tandem.

    apreston0 поблагодарил(а): acm
  • PRO
    Tile Plus, Inc.
    Год(а)/Лет назад: 7

    Hi apreston0,

    Here is the order you should take in remodeling your bathroom:

    1. Demo out the tub/shower unit.

    2. Demo out the sink and floor.

    3. Remove the fixture.

    4. Install a new tub/shower unit.

    5. Install a new floor.

    6. Install a new vanity.

    7. Install a new countertop, sink and backsplash.

    8. Install a new fixture.

    In summary, no you do not do the floor tile last. More like the middle.

    Regards,

    Tile Plus, Inc.

    apreston0 поблагодарил(а): Tile Plus, Inc.
  • apreston0
    Автор
    Год(а)/Лет назад: 7

    Thank you very much....I'd like to be able to use the bathroom while having the repairs done if at all possible.